Lowell Thomas chairlift – Follow the Progression

Last Update – September 17, 2018

Here is an overview of the progression.


Last Update – September 8, 2018

Here is an overview of the progression.

  • Delivery of return station components.

  • Beginning of the assembly of the return station.

  • All components received to date have been assembled at the summit.

  • The foundation of the last tower was finally poured.

  • Delivery of the 74 chairs.

  • This Saturday, we managed to deliver a 75,000-pound crane to mid-mountain.

  • The crane unloads its equipment and the Géopieux team prepares to drive the 11 piles to support the foundations of the lower terminal.


Last Update – August 31, 2018

Here is an overview of the progression.


Last Update – August 25, 2018

Here is an overview of the progression.


Last Update – August 20, 2018

Here is an overview of the progression.

  • Backfilling of the front foundation and rear footing at the top of the lift.

  • Installation of the braces of the rear pylon at the summit which were poured August 10th.

  • Full day with the team from Helicarrier pouring the foundations for towers 3 through 9.


Update – August 13, 2018

Here are several photos of the project progression.

  • Unloading of seven containers from Austria.

  • Removal of formwork on the front pylon of the summit terminal and preparation of the footing of the rear pylon.

  • Inspection of the rear pylon reinforcement.

  • Pouring of the rear pylon footing.

  • Removal of the rear footing formwork.


Update – August 6, 2018

Here are several photos of the project progression.

  • Cleaning the rock after a heavy rain in preparation for the installation of the anchors

  • Anchors installed.

  • Pressure testing of the anchors.

  • Formwork construction of the front pylon at the summit terminal.

  • Concrete pouring for the front pylon at the summit terminal.

  • Drilling for soil tests for foundations of the base terminal.

  • The engineer characterizes the different layers of soil to know their carrying capacity.

  • Delivery of 3 containers from Austria with components for the terminals.


Update – July 27, 2018

Here are several photos of the project progression.

  • Formwork removed on tower 10.

  • Formwork removed on tower 11.

  • All formwork completed with the exception of T1 which will be completed at the same time as the base terminal.

  • 50mm of rain has created a small lake at the summit.

  • The water needed to be pumped to locate the holes which needed to be drained with compressed air.

  • It was then possible to install the anchors.


Update – July 20, 2018


Update – July 12, 2018

The preparatory work is moving along at a good pace! Following the survey work to position the twelve towers, excavation for the foundations of the towers and terminal at the base of the lift was completed. Excavation allows engineers to characterize soils in order to opt for the right type of foundation. As an example, excavation revealed rock surfaces that present a challenge and require customized solutions.

When rock was found at the tower locations, it was drilled to install anchors. These anchors are sealed into the rock and pulling tests are then carried out to ensure their solidity. In order to pour the concrete, plywood forms were built with specific dimensions for each tower. Along the way, we discovered that some artificial snow pipes were located too close to tower 11 and had to be relocated.

  • Forms for each tower

  • Drilling and installation of anchors

  • Snow pipes of tower 11

Last week, a second team was thus still working on relocating the snow pipes at the top of the lift to make way for the terminal. Waiting for delivery of the steel pipes delayed the progress of the work. The pipes finally arrived last Tuesday after 8 p.m. At least, the team managed to enjoy an incredible view and a beautiful sunset!

  • Relocating the snow pipes at the top

  • Delivery of the new pipes

Here is a glimpse of a foundation that is ready for its new tower!


Update – June 21, 2018

Work continues on the Lowell Thomas lift replacement. Rain or shine, the team is giving its best efforts to meet the project schedule.

An access road has been built from the bottom of the lift to the summit to carry equipment up and down during the installation. On the long term, this road will also be used for operations, lift maintenance and for transportation of other mountain equipment.

The construction site is starting to take shape! The Doppelmayr team arrived on the week of June 5 with all the essential equipment to install the new lift. After its arrival, land surveying began to determine the exact location of the new towers.

  • Arrival of Doppelmayr

  • Arrival of Doppelmayr

  • Land surveying

  • Land surveying

In just a few days, we excavated to install the towers and are now building the forms for their foundations. Engineers are making final adjustments before installing the lift towers. We’ve also changed the location of the artificial snowmaking pipes in order to move them away from the terminal at the top of the lift.

  • Excavation of the new towers

  • Moving the artificial snowmaking pipes

  • Forms for the foundations

The installation of the new lift is moving along very well!


Update – April, 2018

The first stage consisted in removing all the chairs. Our team sorted the parts to be either recycled or used as spare parts for the Porte du Soleil lift.
Removing the chairs

Removing the chairs

Cables were then unhooked from the sheave assembly to be removed. Since this cable could not be assigned to another lift, it was cut into small segments for recycling. Then, we disassembled and cut the lift towers that will serve as drainage pipes at various locations on the mountain.

  • Unhooking of the cables

  • Unhooking of the cables

  • Unhooking of the cables

  • Disassembly and cutting of the towers

  • Disassembly and cutting of the towers

Large equipment such as the electric motor and transmission will also be saved as spare parts for the Porte du Soleil lift. It is also the beginning of a new life for the diesel engine that will serve as an emergency generator.

When the ski season ended, we were able to complete the dismantling of terminals and began the foundations’ demolition. Once again, most of the components will be reused to minimize the environmental impact.

  • Dismantling of the terminals

  • Dismantling of the terminals

  • Dismantling of the terminals

  • Demolition of the foundations

By the end of the month, the new lift’s manufacturer will mobilize its construction team. Frequent updates will be posted throughout the summer to allow you to follow the progress of this project!


As announced earlier on March 12, Alterra Mountain Company is planning major investments in its properties. For Mont Tremblant Resorts and Company, this means replacing the Lowell Thomas chairlift, renovating and expanding the Grand Manitou, opening of new glades, renovating the Fourchette du Diable on the North side as well as other additions and improvements.

Work on the Lowell Thomas lift has already begun and we wished to keep you informed on the progress.

What is being done?

The chairlift will be entirely replaced by a new detachable high speed quad chairlift from Doppelmayr. The lift’s hourly capacity will be increased by 600 skiers, bringing it to 2400 skiers per hour. Dismantling of the lift started on April 9. Abundant snow accumulation allowed for swifter and safer transportation.

Se joindre à la discussion